Activity schedules in construction contracts
![]() |
The term ‘activity schedule’ appears in contracts such as the NEC (New Engineering Contract) Option A contract and in a number of standard lump sum contracts. In FIDIC contracts (Fédération Internationale des Ingénieurs-Conseils), it could be interpreted as fulfilling the requirements of the schedule of payments in a lump-sum contract.
In essence, it relates to a programme where each activity is allocated a price and interim payments are made against completion of each activity. Its advantage is that it simplifies the administration of the interim payment process.
The activity schedule on these types of project is submitted together with a contract programme as part of the tender. It is important that all the activities priced add up to the tender sum and that major sub-contractors participate in the allocation of prices against their programmed activities. This may include payments for off-site goods and materials.
The simplest way to prepare an activity schedule is to draw up a bar chart (Gantt chart) which covers all the main activities required, separating each element of work that is sub-contracted. Some preliminaries, such as site offices, need a separate price bar for set up, operational use and dismantling activities. Other preliminaries such as staff and electrical consumption will be part of a constant bar.
Bars that are longer than a month then have their bar line split by defining more accurately the piece of work completed in that period. A time-defined period is acceptable in the case of preliminaries. The price allocated to each total element of work is then proportionately split to match the more defined elements.
The client’s cost consultant must ensure that the pricing of the activity schedule is not unduly front-loaded and fairly reflects normal cash-flow curves associated with building projects.
The contract conditions normally allow the contractor a short period of time after appointment to re-visit the activity schedule to expand its detail. In addition, during the course of the project, the activity schedule can be adjusted to accommodate variations, extensions of time and compensation events.
The preparation of a monthly submission for interim payment is best achieved by the contractor's project manager walking the site with the client’s representative to agree progress in respect of completed activities. Here some judgement needs to be exercised by the client’s representative as to what is ‘complete’, otherwise, strictly speaking, on a 100% basis the contractor would suffer massive cash-flow problems due to the withholding of payment.
Once the progress chart against the programme has been agreed it becomes a simple mathematical calculation of the relative prices to arrive at the valuation and its certification.
NB: Within the NEC3 Engineering and Construction Contract (ECC), The 'accepted programme' shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date. See accepted programme for more information.
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Accepted programme.
- Baseline programme.
- Conditions of contract.
- Construction contract.
- Contractor's working schedule.
- Gantt chart.
- How progress is agreed in construction.
- Interim payment.
- Line of balance (LOB).
- Milestones.
- NEC Option A: Priced contract with activity schedule.
- Off-site goods and materials.
- Preliminaries.
- Procurement route.
- Programme.
- Programme consultant.
- Progress in construction.
- Resource management.
- Schedule.
- Schedule performance index (SPI).
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time management of construction projects.
- Topping out.
- Window and door schedules.
[edit] External references
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.